Module 7 of 9 · A5 · Monitoring and reporting at an aluminium installation

7.The monitoring plan

Written in English, with 22 minimum elements. The ones that matter most for aluminium:

  • installation, processes, routes and goods by CN code;
  • benchmarks relevant for the free allocation adjustment;
  • methods, instruments and their locations;
  • source streams per process;
  • the PFC monitoring method (primary smelters);
  • a boundary diagram with no double counting or gaps;
  • precursors and their suppliers;
  • a control system: calibration, data-flow risks, IT controls, internal review, record keeping.

Any "not technically feasible" or "unreasonable cost" justification must be written in the plan.

SIMPLIFIED A plant that only cuts, welds or finishes can keep its plan very short.

Sources: MA Art 5(5)-(6), Annex II A.3 points 7-8, A.5 p.31-33; G5e §3.1.1 p.19.