Module 8 of 9 · S3 · Verification, carbon price paid and the free allocation adjustment
4.Site visits
- First year: a physical visit is always required.
- Virtual visit: possible only after a physical visit the year before, low risk and no significant changes.
- Waiver: needs physical visits in the two previous years plus the same conditions.
- In practice: physical, then virtual every second year, or a waiver every third year.
- Significant changes (new route, new energy supply or precursors, new method) block both options.
- Force majeure also allows a virtual visit.
Sources: REG Annex VI 1(c); VPA recital 3, Art 3(1), 4; AVA Annex II 2.13; GV §4.9 p.61.